  1. To clean burs on the shaft and inner hole of mechanical seals. To make sure those are smooth without burs.
  2. To smear grease on the shaft and inner hole of mechanical seals.
  3. Install mechanical seals onto shaft. And fasten bolts on the flange,evenly(Don’t fasten one bolts very deep at first time, you need fasten them one by one, and strength bigger and bigger, untill all bolts fasten together)
  4. Fasten bolts on clamp ring.
  5. Disassemble limited block  
  6. Input cooling water before operate mechanical seal. Ensure cooling water normal operation. The pressure of cooling water should be more than media 1 bar. For example, if pressure of your media is 0 bar, the cooling water should be 1 bar.

 

Reactor Mechanical Seal Installation Steps

Shale Gas Exploitation Project

Meet with customers from Bahrain

Contact

Wechat/whatsapp: +86-17383458273
Skype ID: keyuseal_1
High tech Industrial Zone, Zigong City, Sichuan Province, China

KEYU SEAL

We are large manufacturer and exporter of high pressure,high temperature, high speed mechanical seal.

We can provide ODM and OEM precision machined parts according to your drawings or design requirements.